Construction and installation work
Fabrication and delivery of equipment and materials
General staff mobilization: 2 024 people
Completed work:
The design, manufacture, supply of equipment and construction and installation work have been completed.
Commissioning works are underway
Project is implemented by:
Karabatan Utility Solutions LLP
Consumption "KPI Inc.":
- Demineralised water: 360 msup>3/h
- Process water: 3 m3/h
- Demineralised water: 56,37 msup>3/h
- the Purification of household sewage:35 m3/h
- Treatment of oily and storm waters: 22 m3/h
- Purification of chemically contaminated wastewater: 73 m3/h